Examples — before / after

Grounded transformations showing what the methodology changes in practice. Each ties back to a section in METHODOLOGY.md. Real projects are named where the change actually happened; specifics are illustrative, not exhaustive history.


1. Blank slate → provable history (§4 backfill)

Before: visual-cursor tracked from zero — one open milestone, a few forward issues. The 4-file tool that already shipped looked less mature than it was.

After: one read of the README + shipped source produced 5 Done issues with evidence, in a backfill milestone. Linear now reflects real maturity from day one. → §4 (backfill algorithm), §4.5 (cross-check reconstructs the roadmap).

2. Vibe-check "done" → scoreable done (§18)

Before: "tracking's set up" meant some milestones exist. No way to say whether it was actually complete.

After: score the §18 rubric — orphan issues (dim #4) and no agent-instructions discipline (dim #9) came back at 0, total 13/20 = SOFT. The gaps were named, not guessed. → §18 (rubric), §26 (the audit that produces the score).

3. Project type predicted the wrong structure → the goal did (§7, §17)

Before: visual-cursor was a tiny Tool, so the expected shape was one milestone and a handful of issues.

After: §1b question 5 ("ship to npm and launch") converted it into three tracks — backfill / launch readiness / rollout — with real cross-track blockedBy relations. Size predicted nothing; the meta-goal predicted everything. → §17 (shape ceiling vs. meta-goal amount), §7 (launch track keyed off the goal, not the type).

4. Confusing shared labels → namespaced label group (§4, §24)

Before: a Tool's internal-seam labels (stamp/agent/overlay) would land in the same team namespace as Obi's issues, where a bare agent label is actively confusing.

After: a Linear label group named after the project (isGroup + parent), children = the module labels. Cross-project labels (Bug, iOS) stay top-level. → §4 (label groups), §13 (multi-project conventions), §24 (labels answer what part of the code, milestones answer when).

5. Doc says "complete" → live issue says otherwise (§4.8)

Before: Obi's macos-convergence-plan.md closed with "macOS is now one-for-one with iPhone" — which read as evidence to mark the open issue OFF-6 Done.

After: corroborated with the user first; the work was still in progress. Left OFF-6 untouched, logged the discrepancy. A doc's own claim is evidence, not proof. → §4 step 8 (corroborate before a doc overrides a live issue).

6. "Already tracked" → a whole untracked initiative (§22b)

Before: Obi's primary North Star trio was fully mirrored, so the project read as complete.

After: the §4.5 cross-check prompted a docs/ scan that surfaced native-editor-plan.md — a substantial, already-shipped track with zero Linear presence. Filed as its own milestone set (8 milestones, 8 issues), the existing side untouched. → §22b (half-tracked rescue), §4.7 (scan for unmirrored tracks).


Worked example — a deliberately messy project, fixed step by step

"widget-cli" — the mess (fictional, illustrative). A 6-month-old CLI, tracked haphazardly by a couple of parallel sessions:

  • 40 issues, flat — 9 have no milestone at all.
  • 11 milestones, several named Work on parser, More CLI stuff, Bugfixes round 2.
  • 4 issues sitting In Progress for three weeks; two were actually shipped, one abandoned.
  • Every issue body re-types the roadmap from docs/plan.md.
  • 3 target dates, none with an estimate behind them.
  • No always-loaded tracking protocol (CLAUDE.md / AGENTS.md / rules) — which is why it decayed.

Step 1 — audit, don't touch (§26). Enumerate everything, score the §18 rubric: orphans (#4=0), lifecycle rot (#6=0), no discipline (#9=0), anti-patterns live (#10=0). Total 8/20 = FAIL. Emit the gap list. Get consent before writing (§1a).

Step 2 — kill the orphans (§4, §19 issue soup). Assign the 9 milestone-less issues to the right phase, or delete the dead ones. Every issue gets a milestone.

Step 3 — collapse milestone spam (§23). 11 → 4 outcome-named milestones: Phase 1 — Parser, Phase 2 — CLI UX, 1.0 stability, Launch readiness. Rename Bugfixes round 2 out of existence.

Step 4 — fix the lifecycle (§5). The two shipped In Progress issues → Done with evidence. The abandoned one → Backlog with a comment on why. Nothing lingers In Progress without a reason.

Step 5 — de-duplicate the roadmap (§19). Strip the re-typed plan from issue bodies; each issue points at docs/plan.md. One source of truth.

Step 6 — fix the dates (§9, §19 fake precision). Drop the three fabricated dates. Re-set only those that survive an estimate + dependency sanity-check.

Step 7 — wire dependencies (§4). Launch readiness beats blockedBy the 1.0 stability items that gate them. The critical path lives in Linear, not someone's head.

Step 8 — install the discipline (§5). Write the tracking protocol into the repo's always-loaded agent instructions (widget-cli/CLAUDE.md, and AGENTS.md / .cursor/rules/ if those agents are in play) with real team/project/milestone/label names — so the next session can't re-rot it.

Step 9 — re-score (§18/§26). Rubric back to 17/20 = PASS. Post one status update recording the cleanup (§20). Done means the score says so.